TenneT’s TDTR explained: 85% of the grid, 100% of the responsibility

Illustrative image: electricity grid
Asset control & flexibility

TenneT’s TDTR explained: 85% of the grid, 100% of the responsibility

Logo - Withthegrid
By Paul Mignot & Anaïs Wampack
Reading time: 4-6 minutes
TL;DR

TenneT’s Time-Duration-Bound Transport Rights (TDTR) give flexible grid connections, such as battery parks, access to transport capacity for at least 85% of the year at a reduced grid tariff, in exchange for accepting restrictions during the remaining 15%.

The Dutch high-voltage grid is full, but only at peak. For most hours of the year, the same cables and transformers have room to spare.

With time-duration-bound transport rights (in Dutch, tijdsduurgebonden transportrecht, or TDTR), TenneT makes that off-peak residual capacity available to flexible connections, such as battery parks, at a lower grid tariff. In exchange, those connections must accept that TenneT can fully or partly restrict their transport rights up to 15% of the year.

Keeping that last promise, every day, automatically, is where the operational work is.

This article covers what the contract says, what changed in 2026, and how you can ensure that your site will stay within a changing limit.

What does a TDTR contract give you?

A TDTR contract gives a connection on TenneT’s high-voltage gridSource: TenneT. (2025, April 7). Time-dependent transport rights (TDTR). the right to consume or feed-in for at least 85% of the hours in a year. During the remaining 15%, TenneT may impose a full or partial restriction, for example around expected peaks, with a notice at least one day in advance.

Term What applies
Guaranteed availability Transport rights for at least 85% of the contractual hours; the exact capacity available in the remaining 15% can be reduced or withdrawn.
Notice of a restriction At least one day before the restriction takes effect; the operational release time is 07:00 the day before delivery.
Unit of account Clock quarter-hours (previously hours), following the 2026 ACM code change.
Tariff No charge for the contracted TDTR transport capacity (kWcontract); TenneT expectsSource: Solar & Storage Magazine. (2025, April 7).TenneT vindt 9 gigawatt ruimte op stroomnet, genoeg voor 40 procent nationale piekvraag. flexible users may save up to 65% on grid tariffs when TDTR is combined with time-dependent tariffs.
Who offers it Only TenneT, to connections on its high-voltage grid (110 kV and up).
Where At locations where TenneT has identified residual capacity; it is not automatically available at every TenneT-connected site.
Technology Neutral, though battery parks account for most applications.

What’s the difference with a CBC?

TDTR works in the opposite direction from Capacity Control Contracts (CSC).A CSC means a capaciteitssturingscontract — in English, a Capacity Control Contract (CSC). It is a contract with a grid operator under which a large electricity user, generator, or storage asset agrees to adjust its power use or feed-in when the local grid is congested, in return for compensation.

Under a CSC, you receive compensation for reducing your transport feed-in or demand when TenneT requests it. But with TDTR, you never held an unconditional right to use the grid during restricted periods in the first place; instead, you receive a lower tariff in return for accepting that limitation. As the Dutch government told parliament,Source: Hermans, S. (2025, May 6). Vragen van het lid Erkens (VVD) aan de minister van Klimaat en Groene Groei over het artikel “Toch ruimte op stroomnet, flexibele bedrijven sneller aangesloten” [Aanhangsel van de Handelingen 2024–2025, nr. 2101]. Tweede Kamer der Staten-Generaal. the product is meant to fill leftover room, not to relieve peaks.

In practice the two are combined: TenneT also asks TDTR customers to sign a CSC and a redispatch bid-obligation contract, because the actual need for flexibility can exceed 15% of the time. That extra flexibility is compensated.

Additionally, customers of regional grid operators cannot choose TDTR. Their counterpart is time-block-bound transport rights (TBTR), which allocate grid use in defined time blocks.

How much room is there, and who gets it?

TenneT identified 9.1 GW of residual capacitySource: TenneT. (2025, April 7). TenneT provides 9 gigawatts capacity on the high-voltage grid for customers on the waiting list. suitable for TDTR, including 4 GW on the 220 and 380 kV grid and 5.1 GW on the 110 and 150 kV grid.Source: Solar & Storage Magazine. (2025, April 7). TenneT vindt 9 gigawatt ruimte op stroomnet, genoeg voor 40 procent nationale piekvraag.

The interest largely exceeded that availability. TenneT reported that the total applications exceeded 70 GW, and now states that the TDTR capacity has been fully allocated.

TenneT allocates capacity according to the waiting-list queue on a “first come, first served” basis.*with room for societal prioritization Because stations in a meshed grid share the same residual capacity, it ran iteratively:

  1. TenneT offers capacity to the first applicant in an area.
  2. That applicant has a limited period to decide.
  3. TenneT recalculates what is left.
  4. TenneT contacts the next applicant in the queue.

Note that applicants may also receive partial allocations.

What does the contract ask of you?

With a TDTR contract, your usable grid connection limit can change on a daily basis. Some operational points you need to know:

  • The release deadline is now set to 07:00, the day before delivery.
    The ACM’s 2026 code changeSource: Autoriteit Consument & Markt. (2026, May 7). Codebesluit operationalisering TDTR (tijdsduurgebonden transportrecht). moved the release deadline earlier, so TDTR holders still have time to adjust their FCR auction and participate in relevant balancing markets.
  • “No news is good news”.
    TenneT will only send a message when you must reduce your limit. Nothing received? No restriction.
  • The count is set in quarter-hours.
    The same decision moves availability and the 15% tally from hours to quarter-hours,Source: Autoriteit Consument & Markt. (2026, May 7). Codebesluit operationalisering TDTR (tijdsduurgebonden transportrecht). in line with the 15-minute balancing and wholesale markets. A restriction shorter than an hour therefore no longer consumes an entire hour of the 15% allowance. The end time also does not need to be at a full hour mark.
  • Restrictions can last long.
    Restrictions could, in principle, add up to almost two consecutive months,Source: TenneT. (2025, April 7). Time-dependent transport rights (TDTR). each announced one day prior.
  • Overruns can cost money.
    A TDTR agreement may include contractual or technical measures to prevent transport outside released periods. The precise consequences of exceeding a limit (such as contractual penalties, required technical measures, or tariff effects) depend on the individual connection and transport agreement.
  • The connection may include more than one right.
    A TDTR can sit alongside a firm slice on one connection (firm capacity can be converted to TDTR), and fully variable rights can be added in congestion areas. Taken together, this means the site needs something that turns each release message into a limit for the right quarter-hours and holds the whole connection under it while the battery keeps trading in whatever room is left.

How do you safeguard the limit on site?

Withthegrid provides the security to meet the TDTR limitations. For each site, a project team analyzes the specific TenneT requirements and develops an adequate control strategy. The site specific control strategy is configured on the Teleport Utility, the on-site controller, and is extensively tested before being put into operation.

Once in operation, the 24/7 monitoring services ensure maximum update and availability in line with TenneT’s requirements.

How does this work in practice?

The Teleport Utility enforces a power limit at the grid connection that can change over the day, separately for feed-in and consumption. We call this “dynamic capacity limiting”. The limitation has a limit, a start time and an end time.

The dynamic limit is enforced on-site through one command, setNodeConstraints:

  1. TenneT announces the restricted hours by 07:00 the day before delivery.
  2. Your trader, EMS or operations team schedules a setNodeConstraints command for those periods through the Teleport API.
  3. During those periods, the Teleport holds the site within the configured limit, measured at the grid connection or a designated metering point.
  4. When the period ends, the limit reverts automatically to its default.

Consider a site with a 20 MW firm slice and an 80 MW TDTR slice that is instructed to stay within its firm capacity between 17:00 and 20:00. With a 5% operational margin, the controller would enforce a 19 MW limit for both directions of transport during that window:

{
  "type": "setNodeConstraints",
  "operation": {
    "activePowerLimit": {
      "instantaneous": {
        "feedIn": 19000000,
        "consume": -19000000
      }
    }
  },
  "startAt": "2026-12-08T17:00:00+01:00",
  "endAt": "2026-12-08T20:00:00+01:00"
}

(Values are in watts)

For a site with a TDTR, a few properties of this setup matter in practice:

  • Feed-in and consumption are limited separately.
    A battery hits the grid in both directions, and so does a TDTR restriction.
  • Layers are supported.
    The command can carry an instantaneous limit, a contractual limit or both. This maps onto a connection that stacks firm, TDTR and variable rights.
  • Trading carries on underneath.
    The command runs alongside battery dispatch schedules. When both apply, the lowest active limit wins, so the battery keeps earning inside the remaining room.
  • The limit is held on site.
    The limit is held on site and keeps working if the connection drops after the schedule has arrived.
  • The setup is redundant.
    For maximum availability, there is an automatic fail-over to a second controller in case the first one encounters any issue.

The Teleport is already TenneT-certified as an RTU gateway for BESS on the transmission grid, so one installation covers both grid compliance and the flexible contract.